REPAIR WORK & 

ADDITIONAL WORK

93 Tuas Bay Drive Level 4, Level 1, M1, 2M, 4M, Roof & Building 

​

​

Duration 

4th Sep 2018 to 3rd Dec 2018

​

Main Contractor for the project. The works included:

  • Repair external seepage wall

  • Waterproofing works

  • Painting works

  • Additional works

​

​

​